Report - Project Status

Report - Project Status

Menu : EazeHR > Reports > Project

This is an important report if you want to review the financial status of a project. You can generate this report by
  1. Project wise : summary of all projects can be seen together
  2. Charge code wise : breakup separate reports for each project
  3. Employee wise : separate reports for each project
  4. Employee-Charge code wise : for each project for each employee and charge code combination the cost and billing details are given
  5. Customer wise : separate reports for each project

Records for different tenures are given in separated rows in Employee wise and Employee-Charge code wise option. The data in this report includes submitted and approved timesheets, returned timesheets are not included in the calculations.

Project Wise


% Project Profitability = (Amount Billed - Cost Booked) / Cost Booked

Employee Wise


% Resource Profitability = (Amount Billed - Cost Booked) / Cost Booked.
If a resource has been mapped to a project for multiple tenures with different rates / costs and additional field - Aggregate Resource Profitability is shown where the overall profitability across all deployments is shown.

Charge Code Wise


% Project Profitability = (Amount Billed - Cost Booked) / Cost Booked

 Customer Wise


 % Customer Profitability = (Amount Billed - Cost Booked) / Cost Booked

Employee-Charge Code Wise




    • Related Articles

    • Report - Project Master Data

      Menu : EazeHR > Reports > Project This report gives details of all the Projects created in the Project module. Through Type of Report = Project Master you can get the details of all projects. Through Type of Report = Charge Code mapping you can get ...
    • Report - Project Mapping

      Menu : EazeHR > Reports > Project This report shows mapping of employees to a project during a date range. The From Date / To Date is linked to the Project From Date and To Date. You can also see the planned loading of the employee on the project ...
    • Project overview

      Project modules is used to - create projects : projects can be customer specific, can have a budget in terms of number of hours which are to be spent in each type of activity and a target end date - deployment of employees on projects - track status ...
    • Report - Charge Codes

      Menu : EazeHR > Reports > Project This report gives details of all the Charge Codes created in the Project module.
    • Report - Roll Off Plan

      Menu : EazeHR > Reports > Project This report shows the date on which employees are scheduled to roll off or have rolled off from a project. You can see the roll off report for active and resigned employees for future or past. Maximum date range for ...